NTN Bower Manufacturing Facility

Back

Project Details

City:

Macomb

State:

IL

Size of Project:

243,00 sqft

Duration:

10 Months

Project Type:

Design/Build

Revit/BIM:

No

Power Distribution:

(1) 1200a 15kv Switchgear (3) 3000kva Transformers (3) 4000a 480/277v MSB’s (130’) 1600a Bus Duct (590’) 1200a Bus Duct (390’) 1000a Bus Duct (100’) 800a Bus Duct

Special Systems:

Paging System Fire Alarm

Equipment Hookups:

Dock Doors and Equipment (1) 250hp Air Compressors (1) 150hp Air Compressors HVAC Chillers Welding Receptacles Battery Charging Stations